ABOUT  THE BRIDGE

For many years, there has been discussion about joining the east and west ends of the city with a third route – a bridge over the Cataraqui River.

The two existing routes from east-to-west are Highway 401 and the Lasalle Causeway – neither is owned by the City.

In 2013, an environmental assessment was finished to determine:

  • The need for a third crossing
  • The impacts a third crossing could have on the natural, social and economic environments
  • The best location for the bridge
  • The bridge design concept (Arch with V-Piers)

Frequently asked questions

The most commonly asked questions about the Third Crossing will be posted to the FAQ page over time.


Benefits of a third crossing

The environmental assessment found benefits of a bridge would be to:

  • Increase travel time savings while reducing greenhouse gas emissions
  • Decrease traffic congestion along the Lasalle Causeway
  • Provide additional access to the east end of the city for emergency vehicles and City services
  • Provide an alternative route during Lasalle Causeway closures
  • Provide an opportunity for active transportation with a multi-use trail
  • Accommodate future growth
  • Enhance the Rideau Canal

Location

The environmental assessment studied a range of factors affecting location including: neighbourhoods, marine life, plants and wildlife, shorelines, noise, watercraft navigation, intersection with other transportation routes and more. 

Based on its findings, the best location for a bridge is a link between Gore Road and John Counter Boulevard.


Timeline

There are four key phases of the project.

  • Phase I - The environmental assessment.
  • Phase II - The preliminary design phase – began in February 2016.
  • Phase III - Developing a business plan is the third phase and overlaps with phase II.
  • Phase IV - This plan will be developed if council directs staff to move forward with the project.

Cost

Construction costs for the proposed bridge are estimated at $120 million plus tax (2011 dollars) for a two-lane crossing with an accessible, multi-use trail for active transportation. 

Due to the significant capital costs associated with the Third Crossing, provincial and federal government grant funding has been identified as a major component of the anticipated funding for the overall project.

The cost estimate will be refined as the city progresses through the Third Crossing Action Plan.

Read more information on Cost-benefit analysis.

Project team

City of Kingston team

The City employees responsible for oversight of this project are:

  • Mark van Buren, director of engineering
  • Dan Franco, project manager

Lead consultant

As part of phase II, the preliminary design is being led by J.L. Richards and their team of sub consultants. In addition various agencies and stakeholders will be involved.

J.L. Richards and Associates performing:

  • Project management
  • Civil engineering
  • Transportation engineering
  • Stormwater engineering
  • Electrical engineering

Sub-consultants

  • Parsons - Structural
  • DTAH - Architectural
  • Golders - Geotechnical; geophysical; geo-environmental; bio-acoustics; noise; natural/cultural heritage
  • CSW – Landscape designers
  • Les Higginson – Ontario land surveyor
  • Collins Barrow - Cost Benefit Analysis Consultant

Agencies

For more information on this project, see the Third Crossing phases page.


Project News

Asset Publisher

The final designs for connections to the Third Crossing bridge from the west shore of the Cataraqui River are now available. They include new and impr ...
Today City officials and dignitaries marked the start of in-water construction for the Third Crossing. Mark Gerretsen, Member of Parliament for Kings ...
The City has now posted the final report on environmental considerations for the Third Crossing project. The final ‘Detailed Impact Assessment' (DIA) ...
After working with federal departments and agencies over the past year and the conclusion of a 30-day public engagement process, the city has received ...
Third Crossing bridge to be the first in North America to use an Integrated Project Delivery model After a thorough Request for Proposals (RFP) an ...