Artist rendition of the bridge

Timeline

Current timeline

  • February 2018

    Infrastructure Canada confirms $60 million in funding.
  • May 2018

    Council delegate to staff administrative and contractual authority for property acquisition.
  • June 2018

    New project website is live.
  • August 2018

    Integrated Project Deliver team is formed with the City, Kiewit, Hatch and SYSTRA. Launch of engagement on the City’s Get Involved webpage for the Third Crossing.
  • September 2018

    Information Report to council on procurement process and preferred proponent
  • September - December 2018

    Design validation, environmental investigations - environmental investigations, site preparation, noise mitigation efforts.
  • January 2019

    Presentation on the evolution of the new bridge design.
  • September - December 2019

    Approval of final permit, Detailed Impact Assessment (DIA) by Federal Agencies to begin in-water construction
  • October 2019

    Installation of permanent noise fences on west and east shores.
  • Fall 2019

    Canada Parks Detailed Impact Assessment (DIA). Dates of upcoming engagement coming. Public engagement on detailed design elements of project. Installation of onshore and in-water environmental protection measures (turbidity curtain, silt fencing and five wildlife passages).
  • December 2019

    Ground breaking ceremony and commencement of in-water construction
  • May 2020

    Permission granted by Transport Canada and Parks Canada to work in the navigation channel of the Cataraqui River.
  • June - July 2020

    Hwy 15 & Gore Rd intersection final design completed.
  • June 2020

    Work begins on in-water bridge foundations and abutment.
  • August - December 2020

    Design of Point St. Mark and Gore Rd intersection (south leg) completed.
  • August 2020

    Completion of temporary rock causeway.
  • September 2020

    Work started on pier caps construction.
  • October 2020

    Completion of temporary mainline trestle bridge and the innovative lift span over the navigation channel to accommodate construction work and boat passage
  • 2021 - Upcoming work

    Completion of bridge foundations. Completion of pier caps. Start and completion of concrete girders on bridge approach spans. Start and completion of of steel to be used as part of the main span of the bridge. Start road work on both east and west shores (Hwy 15 & Gore Rd and JCB and Ascot Lane). Start construction on stormwater pond on east shore. Start construction of the bridge deck.
  • 2022 - Upcoming work

    Completion of bridge deck and paving. Completion of road works on west and east shores (paving, signals, lighting, painting). Removal of all temporary works (rock causeway, turbidity curtain, trestle bridge). Opening of bridge for use.
  • 2023 - Upcoming work

    Finalize bridge amenities. Completion of landscaping on west and east shores.

Historical Timeline

  • 1967

    Kingston's Mayor Fray gives an inaugural address that references the need for a Rideau River crossing from Pittsburgh Township.
  • 1978

    Kingston Transportation Study (1978-1993) proposes a new bridge connecting Elliott Avenue and Gore Road.
  • 1993

    Updated Kingston Transportation Study proposes a new bridge connecting Elliott Avenue and Gore Road.
  • 1996

    Ontario government announces its intent to amalgamate municipalities to reduce the number of them from roughly 700 to 444.
  • 1996

    The City of Kingston and municipalities within the County of Frontenac begin the process to reform local governance. As part of this new governance, it is proposed any net savings from amalgamation should be applied to a new 'second bridge crossing' over the Cataraqui River.
  • 1998

    The City officially amalgamates and includes documents that reference the need for a new ‘second bridge crossing' as part of the new City of Kingston.
  • 2004

    The Kingston Transportation Master Plan update proposes a new bridge connecting Elliott Avenue and Gore Road.
  • 2007-2008

    City Council approves the capital budget to start an Environmental Assessment (EA) for a new bridge crossing over the Cataraqui River. Stakeholder and public engagement for the bridge begins.
  • 2009

    City Council approves the start of Stage 1 of the EA.
  • 2010

    City Council approves the start of Stage 2 of the EA.
  • 2012

    City Council endorses the Third Crossing EA.
  • 2013

    The EA is approved by the Ontario Ministry of the Environment.
  • 2015

    City Council approves the budget to start phases two and three. The Third Crossing Action Plan is created to move the project forward with four phases:
    - Phase one – completion of the Third Crossing EA
    - Phase two/three – Preliminary design and business plan
    - Phase four – detailed design and construction
  • 2017

    Ontario Minister of Infrastructure commits a one-third $60M investment towards the Third Crossing.
  • 2017

    Council approves phases two and three of the Third Crossing Action Plan. It allocates a one-third municipal contribution of $60M towards the Third Crossing to start construction pending funding from all levels of government.
  • 2018

    Federal Minister of Infrastructure and Communities commits the remaining one-third $60M investment needed for the Third Crossing. All three levels of government have now come together with equal investments in the project.

More About Us