Princess St. Reconstruction 2018

Nested Applications

Image - City Hall - Projects - Princess St 2018 large

Reconstructed Princess Street Rendering

GENERAL - Heading - City Hall - Projects - About the Project

About the Project

Alert - Princess St Construction

Princess Street is open!
Work continues on Barrie and Division streets. Crews are completing the finishing touches along Princess.

Content - City Hall - Projects - Princess St 2018

Princess Street is Kingston's street.  It's where we go to shop, meet, dine and enjoy our vibrant, lively, healthy and historic downtown. We are built around it. Princess Street is our spine. And we're taking good care of it.

In 2010, the City began remaking history on Princess Street by reconstructing it between Lake Ontario and King Street East. The rebuilding continued in 2013-14 between King Street East and Bagot Street and again in 2016 from Bagot to Clergy. This project is part of the City's Downtown Action Plan.

Updating the above and below-ground infrastructure from building-face to building-face allows the City to build the capacity of its infrastructure to allow for future growth and augment the beauty of this historic street.

2018: Princess Street has been rebuilt from Clergy to Division

Work to completely rebuild Princess Street from Clergy to Division ended with the reopening of Princess to through traffic on July 1, 2018. Crews continue to complete finishing touches along Princess, including adding street furniture and bike racks.

This project continues on the side-streets and includes the rebuilding of:

  • Barrie Street from Princess to Queen
  • Division Street from Brock to Colborne

The City is working closely with business owners to minimize disruption.


2018 project facts

  • Sanitary pipe – 800 metres
  • Storm pipe – 800 metres
  • Watermain – 1,000 metres
  • Asphalt – 9,200 metres
  • Concrete sidewalks – 3,500 sq metres
  • Granite curbs – 700 metres

See the City's 2015 to 2018 Infrastructure Plan for details on other scheduled projects.


Project News

As reconstruction work continues up Princess Street, the intersection of Princess and Barrie streets will be closed starting on Monday, March 12. Ba ...
Where should car parking, bike parking and benches go on reconstructed Princess Street between Clergy and Division? Offer your input at www.GetInvol ...
The final phase of Princess Street guided by the Downtown Action Plan will be reconstructed from building-edge to building-edge starting Monday, Jan ...